Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Landfall operations for Greenlink at both Baginbun Beach (Ireland) and Freshwater West (Wales) were executed using horizontal directional drilling (HDD) methods and were completed during the spring 2024 campaign. HDD allowed the subsea cables to be brought ashore with the duct exits below the low‑water mark, minimising beach and dune disturbance; onshore reinstatement followed standard reinstatement and protection measures.