Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Jan De Nul completed installation, burial and protection of the Greenlink subsea cables between autumn 2023 and spring 2024. The two cable sections were joined at a mid‑sea meeting point; burial works used the project trencher (Swordfish) and support vessel Symphony, and rock protection was placed by the rock‑installation vessel Simon Stevin where seabed conditions prevented trenching.