Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Sumitomo Electric completed installation works and formally handed over the completed HVDC cable system for the Greenlink interconnector to Siemens Energy AG. The handover transferred responsibility for the integrated cable assets to the consortium partner to allow Siemens Energy to complete remaining commissioning, system integration and trial operations ahead of entry into commercial service.