Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
During commissioning of the Greater Gabbard offshore transmission system, the first attempted energisation of the Module 3 export circuit was carried out on 6 August 2010, but a fault occurred after 25 seconds, interrupting the test and requiring subsequent cable repair before commissioning could continue.