Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Fluor awarded a subcontract to Heerema / McNulty for the fabrication of the offshore substation platform (OSP) topsides for the Greater Gabbard transmission assets, providing the structures that house the high-voltage equipment on the two offshore substations connected into the 132 kV export cable system.