DNV KEMA’s ex‑post assessment records 10 September 2012 as the Final Project Completion date for the Greater Gabbard offshore transmission assets, marking the end of construction and commissioning of the two offshore substation platforms, three 132 kV subsea export cables, the 132 kV inter‑platform cable and the Greater Gabbard 132 kV onshore substation connecting to National Grid at Leiston.