Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Onshore construction for the Great Belt (Storebælt) HVDC power link between Eastern Denmark (Zealand) and Western Denmark (Funen) started in spring 2008, with works including the 600 MW, 400 kV connection to the transmission grid at Herslev on Zealand and Fraugde on Funen proceeding on both sides. The construction period was planned to run through to 2010, with station works and land cable installation reported as underway and progressing as planned.