Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In July 2009, JD-Contractor A/S commenced installation of the Great Belt Power Link’s 32 km submarine HVDC cables across the Great Belt, using the cable‑laying barge C/B Henry P. Lading to plough the cables about 50 cm into the seabed along the pre‑trenched route.