Great Belt II is an internal Danish transmission project candidate listed in ENTSO-E planning documents. It is described in regional planning material as an HVDC connector between the Denmark-West (DKW) and Denmark-East (DKE) market zones intended to increase transfer capacity across the Great Be...
Owners
ENTSO-E’s Baltic Sea Regional Investment Plan 2015 for TYNDP 2016 lists Great Belt II (project 175) as a future 600 MW HVDC interconnector candidate between Denmark-West (DKW) and Denmark-East (DKE), potentially connecting the 400 kV substations at Malling and reconstructed Kyndby, with Energinet.dk as project promoter and an expected commissioning year of 2030.
Showing historic events only. Subscribe for the full timeline including projected milestones.
Upgrade to access detailed cable specifications, supply chain data, projected timeline, financial analysis, and more.
Great Belt II, Great Belt-2, Project 175 (TYNDP), DKW–DKE, Great Belt Power Link 2