ABB successfully completed commissioning of the 105.5 km subsea power link supplying electricity from the Norwegian grid to the Goliat FPSO, including a 104 km static seabed section and a 1.5 km dynamic section. The 75 MW, 123 kV AC cable system, delivered as a turnkey package covering design, supply, installation and commissioning, was verified as ready for operation to provide about half of the platform’s power needs from shore and enable significant CO2 emission reductions compared with local generation.