Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 17 December 2024, Prysmian signed a framework agreement with French TSO RTE for the engineering, procurement, construction, installation, and commissioning of the submarine and land high‑voltage AC export cable links connecting the Fos offshore wind project to the French transmission grid, comprising three 225 kV three‑core export cables with XLPE insulation and around 300 km of land and submarine cables for the Fos connection, rated at 750 MW.