Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 26 February 2026, Skyborn Renewables signed a firm contract with a consortium of Boskalis and TKF for the complete inter-array cable system at Gennaker, under which TKF will manufacture about 140 kilometres of 66 kV inter-array cables in the Netherlands and Boskalis will install them at the German Baltic Sea site using its cable-laying vessel Boka Ocean by the end of 2027.