National Grid delivered the onshore connection at the Leiston 132 kV substation for the Galloper project in the first quarter of 2017, completing the physical onshore grid connection works ahead of transmission asset commissioning. The project achieved first power in November 2017, confirming these works were completed. Note: date is from pre-event projection (Ofgem PIM Sep 2016); no post-event source found to verify exact timing.