Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In the same Galloper project update for Ofgem’s Tender Round 5, Galloper Wind Farm Ltd stated that the second 132 kV subsea export cable for the Galloper offshore transmission system was still in manufacture but scheduled and ready for installation in Q2 2017, indicating a planned continuation of the export cable installation works for the Galloper OFTO assets.