Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Nordic Grid Development Perspective 2025 (prepared by the Nordic TSOs) states that, for Fenno-Skan 3, “Prior to entering into contracts for converters and cables, a joint Final Investment Decision expected in 2026/2027 will be agreed upon by [the TSOs]”. Using the latest end of the stated range, this projects joint FID/financial close by end-2027 (range given as 2026/2027).