Fingrid press release announcing Fenno-Skan 2 completion (dated 16 Dec 2011) states that, during the trial operation period, "some of the capacity of Fenno-Skan 2 was made available to the market ... from 15 November onwards"—indicating initial energisation / first power flow began on 15 Nov 2011 (trial operation), ahead of full market availability on 16 Dec 2011.