Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Fingrid Oyj and Svenska Kraftnät planned for offshore installation and laying of the Fenno-Skan 2 HVDC submarine cable by Nexans to start in spring 2011, with work to continue through the summer using Nexans’ cable-laying vessel CS Skagerrak. The 800 MW, 500 kV interconnector’s approximately 200 km submarine section between Finland and Sweden was scheduled to be installed in two continuous lengths of about 100 km each, requiring only a single offshore joint.