On 26 July 2024, Elering submitted an application to the Ministry of Regional Affairs and Agriculture to initiate a national designated spatial plan to upgrade Estonia’s onshore transmission system in connection with the EstLink 3 interconnector. The plan covers grid reinforcements including a new high‑voltage substation near Lake Ülemiste in Tallinn, new 330 kV overhead lines to Aruküla and Kiisa substations, and reconstruction of several existing 330 kV lines to accommodate EstLink 3 capacity and future offshore wind integration.