Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
System testing of the EstLink 2 interconnector was completed in December 2013, allowing the project to move from the test phase into a trial operation period during which the link was already available for commercial use, following earlier completion of cable testing and the start of cross‑border tests between Finland and Estonia in late November 2013.