In response to the December 2024 anchor‑damage incident, Nexans and the TSOs Elering and Fingrid undertook a major subsea repair campaign on EstLink 2 in May 2025. Preparatory work from February to April involved lifting and cutting out the damaged section, after which approximately one kilometre of new spare subsea cable and repair joints were installed from the vessel Deep Cygnus to reconnect the undamaged cable ends, in a repair estimated to cost €50–60 million shared between the two TSOs.