Neutral
Informational - no clear directional impact
Medium Impact
Significant progress or notable issue
Following the January 2024 internal fault at the Estonian coastal section of EstLink 2, Elering and Fingrid carried out a major repair campaign that required replacing approximately 300 metres of oil‑paper insulated cable near the landfall. The work included constructing a new marine cable joint from a coastal platform and completing a transition joint between the marine and land cables, with the repair campaign lasting until early September 2024 at a reported cost of over €30 million.