Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
The Transmission System Operator for the Estlink DC interconnector between Finland and Estonia obtained building authorisation for the power line from the Finnish Energy Market Authority in May 2005, following an application submitted in March 2005. This authorisation, required before construction of the line could start, involved the Authority assessing the necessity of the line and effectively allowed the project to proceed to the building phase.