Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Blue Gem Wind Ltd, the developer of Project Erebus, has entered into a grid connection agreement with National Grid Electricity System Operator (NGESO) for a connection at the National Grid Electricity Transmission (NGET) 132 kV Pembroke substation, which forms part of the wider Pembroke transmission development and will serve the Erebus export cable and onshore substation connection.