Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By the time of the December 2021 Environmental Statement and associated planning documents, Blue Gem Wind had concluded that West Angle Bay on the Pembrokeshire coast was the most suitable and lowest‑risk nearshore export cable route and landfall for Erebus, despite the relatively long onshore cable route and interactions with multiple designated sites, and the project’s onshore CTMP referenced a cable landfall in the vicinity of West Angle Bay with an approximately 14.8 km cable route to the substation near Pembroke Power Station.