Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
On 19 April 2023, Blue Gem Wind commenced the offshore geotechnical survey phase for Erebus’s export cable and array area, with survey contractor Fugro deploying the vessels Voe Vanguard and later Fugro Scout to undertake cone penetration tests, vibrocores, and rotary boreholes to characterise sub‑seabed conditions for detailed design of cables and floating foundation anchoring.