Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
On 6 July 2023, Blue Gem Wind announced completion of the detailed geotechnical campaign for the 100 MW Erebus test and demonstration project, following offshore and nearshore sub‑seabed data acquisition by Fugro using Fugro Scout and the Aran 120 jack‑up barge, with samples sent for laboratory testing to inform detailed offshore cable and anchoring design and preparation for the construction phase.