Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
EnBW selected the FICG consortium, comprising Cofely Fabricom, Iemants and CG, to design, supply and install the offshore substation for the EnBW Hohe See offshore wind farm. Contracted in March 2016, the consortium’s scope includes engineering, procurement, construction and commissioning of the substation topside and jacket, steel superstructure, and high- and medium-voltage equipment and control systems needed to collect and export power from the 497 MW wind farm in the German North Sea.