Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In June 2018, the offshore substation (OSS) for the EnBW Hohe See wind farm was transported from Antwerp to the project site on a pontoon, departing on 20 June. Upon arrival in the wind farm area, the topside was lifted during the night of 27 June 2018 by two cranes on the heavy lift vessel "Thialf" onto the already installed jacket foundation. In the days following the lift, the initial OSS crew completed the installation through necessary welding and additional works, finalising the placement of the substation on its offshore foundation.