Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Offshore construction at the EnBW Hohe See offshore wind farm effectively commenced when Swire Blue Ocean’s installation vessel Pacific Osprey installed the first monopile foundation at the site in the German North Sea, around 95 km north of Borkum and 100 km northwest of Helgoland. This marked the start of the main offshore installation campaign for 71 monopile foundations at Hohe See (plus 16 at neighbouring Albatros) following EnBW’s mobilisation of vessels and foundations from the port of Vlissingen.