By February 2019, installation of all foundations at the Hohe See offshore wind farm had been completed following a temporary interruption caused by a crane accident on the vessel Pacific Osprey. Remaining monopiles and transition pieces were reloaded in Eemshaven using the heavy-lift crane vessel Gulliver, allowing the foundation campaign at the remote North Sea site, roughly 100 km northwest of Helgoland, to be finished.