50Hertz was responsible for the offshore grid connection and awarded the contract for monitoring the submarine power cables to Nkt cables; Baltic 2 grid connection cable length offshore approx. 120 km, 150 kV HVAC.
Nkt cables was awarded a contract by 50Hertz to monitor the submarine power cables forming the Baltic 2 offshore wind farm grid connection. The monitored asset comprised the offshore export cable system (approximately 120 km subsea) connecting the wind farm area to the onshore connection point at Bentwisch substation near Rostock.