Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
According to EnBW’s construction diary for the EnBW Baltic 2 offshore wind farm, on 6 August 2014 a pile forming part of the foundation for the future offshore substation (OSS) was installed at the project site. The entry notes that a pile (described as a foundation component) intended to anchor the later substation was driven and fixed into the seabed. This activity marks a key step in establishing the OSS foundation structure that will support the offshore substation for power collection and export from the wind farm.