Getlink, the owner of the ElecLink interconnector, reached an agreement with its insurers for approximately €55 million in compensation for operating losses caused by a prolonged ElecLink outage from 25 September 2024 to 5 February 2025. The settlement covers revenue lost while the high‑voltage electricity link through the Channel Tunnel was offline for fault investigation and repairs, with €5 million already booked in the first half of 2025 and the remaining €50 million to be recognised in Getlink’s consolidated 2025 financial statements.