By summer 2021, ElecLink had completed pulling its HVDC cables through the Channel Tunnel, with all 2.5 km sections installed along the 51 km route and spliced together in cleanrooms inside the tunnel to form the continuous interconnector circuit between the Folkestone and Peuplingues converter stations.