Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
In November 2019, the environmental authorisation (autorisation environnementale) for RTE’s grid connection of the EFGL floating wind pilot project in the Golfe du Lion was granted, covering the 63 kV submarine and underground export cable linking the offshore wind farm area near Leucate and Le Barcarès to the existing Salanques substation.