Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
RTE’s 5 March 2023 project update reports that on Sunday 5 March at Le Barcarès, the fourreau (duct) for the future 63 kV export cable of the Éoliennes flottantes du golfe du Lion (EFGL) project was put in the water, marking the first offshore works (“premiers travaux en mer”) for the export connection. This corresponds to the start of offshore construction for the EFGL export cable.