Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Commercial operations (full power) projected for end of 2026 for the EFGL 30 MW floating wind pilot export connection. As of November 2025 all three WindFloat T platforms with Vestas V164-10 MW turbines had been installed offshore and the 63 kV export cable (Oct 2024) plus onshore civils (2022) were complete; Principle Power's official project page lists 'First power 2026', implying commissioning continues through 2026 with full commercial operations by year-end. Delayed from a stale 2025-12-31 projection that slipped past due without a projections agent update.