Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In March 2023, NKT completed the power cable systems connecting the Edvard Grieg offshore platform to the Utsira High power-from-shore solution via Johan Sverdrup, finalising the cable connections that provide electricity from shore to Edvard Grieg and other platforms in the area. This milestone marked the completion of the Utsira High electrification cabling campaign, enabling onshore power supply to six offshore installations including Edvard Grieg and Ivar Aasen.