Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
National Grid published emerging preferences for Eastern Green Link 4 during a non-statutory public consultation that opened on 23 April 2024 (running to 15 July 2024). The consultation presented preferred landfall options (Theddlethorpe or Anderby Creek), candidate locations for converter stations (including a Lincolnshire option northeast of Bilsby) and indicative onshore cable corridors; these emerging preferences were used to inform further routeing and environmental assessment.