Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
EGL2 (SSEN Transmission/National Grid joint project) commenced offshore marine survey work in 2024 with its main works contractor Prysmian. The programme comprised geophysical, geotechnical and environmental surveys along the planned subsea cable corridor between Peterhead and Drax to map seabed conditions and inform routeing and installation planning ahead of subsea works scheduled for 2027–2028. Survey activity used specialist survey vessels and fed into detailed route engineering and mitigation planning.