As part of pre‑installation activities, EGL1's Environmental Appraisal Report set out a UXO management strategy and the requirement for site‑specific unexploded ordnance (UXO) surveys from 2024 onwards. The approach included desk-based assessment followed by targeted UXO survey work in areas of moderate and high risk, identification and verification of potential UXO (pUXO) targets and, where necessary, seabed excavation using divers (<10 m) or ROVs (>10 m) and clearance (including controlled detonation under separate consents) prior to further works.