On 9 April 2025 Ofgem published a consultation recording that the EGL1 joint venture had applied for an ASTI ODI Penalty Exemption Period after seeking a 480‑day exemption, citing global unavailability of equipment and supply‑chain capacity. The consultation noted the JV’s claim that these supply‑chain constraints had delayed delivery and recorded that the project’s current expected delivery date was April 2029 (around 16 months later than previously required). Ofgem published its provisional view and sought stakeholder responses on whether the delay qualified for exemption.