Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
A marine licence decision letter for the project was issued on 20 July 2023 (marine licence reference L/2023/00212/1), representing the licensing authority's determination on the marine permit for the subsea cable. The decision followed the 2022 marine licence application and associated Marine Environmental Reports submitted by the JV to enable the subsea installation and associated marine works.