Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Project communications stated that comprehensive marine geophysical surveys (MBES, SSS and sub-bottom profiling) for EGL1 were slated to run from Q2 through Q4 2025 to provide the data required for final design and engineering of the subsea route. The planned end-of‑Q4 2025 completion reflected the programme for nearshore and offshore survey activities within the marine installation corridor ahead of installation works.