Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Landfall operations for EGL1 were planned to be completed as part of the offshore campaign and were to be delivered using Horizontal Directional Drilling (HDD) to install conduits beneath the intertidal zone at the Torness and Seaham/Hawthorn Pit landfall locations. HDD was selected to minimise intertidal works and environmental impacts; completion of landfall works was expected to be achieved during the broader subsea installation programme.