Negative
Setback or risk materialised
Medium Impact
Significant progress or notable issue
In March 2022, after a planned three-week shutdown, the East–West Interconnector remained operating at below 1% of its capacity for an ongoing period, indicating a significant reduction in available transfer capability following maintenance.