66 kV inter-array cables connecting up to 64 turbines to offshore substation
Hellenic Cables, the cables division of Cenergy Holdings, secured a contract from Seaway7 to engineer, design, manufacture, test, and deliver approximately 165 km of 66 kV submarine inter-array cables and associated accessories for the East Anglia TWO offshore wind farm. The cables will form the inter-array network connecting up to 64 turbines to the offshore substation in the southern North Sea. Production is scheduled at Hellenic Cables’ submarine cable plant in Corinth, Greece, starting in 2026 with final deliveries planned for the first half of 2027, supporting Seaway7’s wider transport and installation scope for the project.