Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In November 2023, HSM Offshore Energy was appointed to design and construct the offshore substation for the East Anglia TWO project, providing the main offshore electrical platform that will collect turbine output and feed it into the export cable system to shore.