Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
ScottishPower Renewables commenced onshore construction works for East Anglia TWO with the installation of underground duct banks for substation cabling on the B1069 Snape Road near Knodishall, Suffolk. A temporary road closure was in place across three weekends starting 20 September 2025. Prior enabling works including ecological mitigation, archaeology investigations, and highway access improvements had been underway since mid-2024.