WNoO #016/2026 — as-built 2026-04-20 Progress: monopile foundations 58/95; transition pieces 58/95; OFCS jacket+topside complete (jacket 11/08/2025, topside 16/10/2025) and in active commissioning; WTGs 1/95 (location C17, MP 14/10/2025, TP 15/10/2025); inter-array cable lay, trench/burial and termination/testing all active concurrently; no IAC string commissioning state published. WTG Commissioning Campaign formally opened 01/04/2026 per NTM 012/2026. This period: continued MP/TP installation by Seaway Ventus; TP completion (bolt tensioning, grouting) by Norside Supporter; first WTG complete at C17 with Wind Osprey; IAC lay support via W2W from Seaway Moxie; trenching by Grand Canyon III; termination/testing by Windea Clausius; OFCS commissioning supported by JB 120 (accommodation jack-up) and Bos Prelude (PSV); IWS Windwalker on-station as WTG commissioning SOV; Farra Siskin completed push-on trials. Forecast next 7 days: WTG installation continues at C18/C20/A05/A06/A08; Wind Pace mobilising from Esbjerg for WTG installation; Seaway Phoenix mobilising from Eemshaven for IAC lay; Grampian Eagle joining as OFCS PSV per NTM 017/2026. Active fleet: TIV Wind Osprey, Wind Pace (mob); CLV Seaway Moxie, Seaway Phoenix (mob), Windea Clausius; cable trencher Grand Canyon III; foundation install Seaway Ventus; TP completion Norside Supporter; SOV IWS Windwalker; CTVs Farra Siskin, Fob Swath 7, NR Hunter, NR Rebellion, NR Predator; PSV at OFCS Bos Prelude, Grampian Eagle (mob); accommodation jack-up JB 120; ERRVs Esvagt Cobra, Esvagt Carpathia (standby); Guard vessel GV Tess. Source: WNoO #016/2026 dated 20 April 2026, ScottishPower Renewables.